New Jersey DEP Resources
Click on the links below to access the documents:
Permit Applications
Environmental Justice Information Session Resources
Facility Permits
Compliance History
Compliance History
- October 9, 2020 - Official Administrative Consent Order (ACO)
- November 6, 2020 - ACO Response Submittal Package 1
- November 19, 2020 – Condition (a)1 of Phase II, Section B of ACO
- December 30, 2020 - ACO Progress Report 2
- January 6, 2021 - Condition (a) of Phase II, Section B of ACO
- January 7, 2021 – Conditions (a) and (c) of Phase I, Section B of ACO
- January 7, 2021 – Condition (d) of Phase I, Section B of ACO
- March 2, 2021 - ACO Progress Report 3
- April 6, 2021 - Response to comments on Iodine Monitor Report
- April 21, 2021 – Response to NJDEP Comments on the Air Quality Modeling Protocol for Iodine Emissions
- April 29, 2021 – ACO Progress Report 4
- June 30, 2021 - ACO Progress Report 5
- July 19, 2021 - Covanta Response to NJDEP Comments on Essex Communications & Community Engagement Plan
- July 20, 2021 - Air Quality Modeling Report
- July 29, 2021 - Halogenated Waste Pollution Prevention Plan
- September 1, 2021 - ACO Progress Report 6
- September 24, 2021 - Covanta Response to NJDEP Comments on Essex Communications & Community Engagement Plan
- October 18, 2021 - Air Quality Modeling Report of Iodine Emissions Assessment
- November 1, 2021 - ACO Progress Report 7
- November 23, 2021 - Essex Communications & Community Engagement Plan
- December 30, 2021 - ACO Progress Report 8
- March 1, 2022 - ACO Progress Report 9
- May 2, 2022 - ACO Progress Report 10
- June 21, 2022 - ACO Progress Report 11
- September 1, 2022 - ACO Progress Report 12
- November 1, 2022 - ACO Progress Report 13
- December 29, 2022 - ACO Progress Report 14
- March 1, 2023 - ACO Progress Report 15
- May 1, 2023 - ACO Progress Report 16
- June 29, 2023 - ACO Progress Report 17
- September 1, 2023 - ACO Progress Report 18
- November 1, 2023 - ACO Progress Report 19
- January 2, 2024 - ACO Progress Report 20
- February 28, 2024 - ACO Progress Report 21
- May 1, 2024 - ACO Progress Report 22
- July 1, 2024 - ACO Progress Report 23
- August 30, 2024 - ACO Progress Report 24
- November 1, 2024 - ACO Progress Report 25
- December 31, 2024 - ACO Progress Report 26
- February 28. 2025 - ACO Progress Report 27
- May 1, 2025 - ACO Progress Report 28
- July 1, 2025 - ACO Progress Report 29
- September 2, 2025 - ACO Progress Report 30
- October 29, 2025 - ACO Progress Report 31
- January 8, 2026 - ACO Progress Report 32
- March 3, 2026 - ACO Progress Report 33
- May 4, 2026 - ACO Progress Report 34
- June 29, 2026 - ACO Progress Report 35